May 2003
What about disruption, we want to be able to keep playing the course while
the work is in progress?
Golf course architect Roger Jones profiles the human side of a remodelling
project at Craddockstown Golf Club in Co Kildare, Ireland, providing an insight
into the planning and attention required, and how when done properly, such a
project can run very smoothly and without disruption.
Background
It was February 1999 and on a cold damp morning, over coffee in the clubhouse,
an outline of the problems and areas of concern was given by Donal O'Keefe,
the Club Captain. A walk of the course followed and the preliminaries of the
design process had begun.
In March of this year construction work finally got under way and will be
finished at the end of June.
The intervening four years have seen a variety of design solution drawings,
cost estimates, development committee meetings, more costings, deliberations
over phased construction or all at one time, questions and answers, Annual
General Meetings and Extraordinary General Meetings - all part and parcel of
the workings and politics of undoubtedly a typical member-owned golf club.
There was a strong desire to redesign, remodel, reconstruct and generally
upgrade the golf course on the part of a number of club officials and members.
Getting the necessary democratic approval for, and being able to finance such a
plan, was a task for another day. There were some club officials and members
who could see no need or no potential benefit in such a project and felt the
club couldn't afford it anyway. Hence four years have elapsed since Roger
Jones of Roger Jones Golf Design was first asked to visit the course to meet
Donal O'Keefe and others. Club Captains and committees have changed but the
people with the ambition and drive to see the project come to fruition have
remained, the aforementioned Mr O'Keefe being at the head of that list.
Mention must also go the lady members of the development committee. At every
stage their contribution was very constructive and very helpful to the
architect, particularly in relation to the siting of tees and other features
that would impact on the lady members' play on the golf course.
Craddockstown Golf Club in Naas, Co Kildare was constructed in the days of
exuberant golf course development in the early 1990s. The development was
funded by the original members, with a limited budget, and unfortunately some
elements of the construction were either not done, not done in accordance with
any kind of recognised specification, or there had been a series of shortcuts
to save cost. Some of this had now reared its ugly head and come back to haunt
the keen and eager golfing membership. In addition the land has an abundance of
natural water that had not been incorporated into the design of the golf course
as fully as it could. That said, had the development cost been any higher at
the time it is unlikely that the golf course would be in existence today. The
same may be true for many golf courses that have been developed in the past ten
or more years.
But the maturing members of Craddockstown - maturing in golf terms that is -
had come to recognise these deficiencies and wanted to do something about it.
Coincidentally, if further proof of their proactive, get up and go approach was
needed, in 1999 they built a brand new clubhouse at a cost of over IR£1
million.
Project Brief
So back to 1999 and the 'brief' that was given to Roger Jones on that
February day. The 13th hole was highlighted as being 'uninteresting and
unnecessarily long', other holes were described as 'featureless',
the par 3's were described as too long and too similar in character, the
course had no fairway bunkers, the ponds did not really come into play, there
were drainage problems in a number of areas and a gravel layer that had been
put into all the greenside bunkers when they were constructed was now coming to
the surface and causing damage to maintenance machinery and members golf
clubs.
Another factor to be considered was that the town of Naas was growing rapidly
and new residential development was getting ever closer to the golf course
boundaries - to avoid potential dangers in the future it may be necessary to
relocate some teeing areas. After taking these primary issues into account
Roger Jones was given a free hand, within reason, to come up with other ideas
that could add to the strategy, playability and overall appearance of the golf
course.
After a number of design proposals and variations, some arising out of new
problems emerging, and variations because of cost implications, the scheme
agreed between Roger Jones and club officials comprised some new greens, new
tees, over 3 acres of additional lakes, new fairway bunkers, fairway mounding,
the reshaping and reconstruction of all existing greenside bunkers, reshaping
of existing open drain and hundreds of metres of new pipe drainage.
Discussion, deliberation, cogitation, and sometimes procrastination was
finally brought to a head by the 2002 Club Captain and chairman of the
club's development committee Brendan Byrne. Brendan decided that during his
term of office it was time for the club to either 'put up or shut up'
or 'pee or get off the pot'. Exactly which phrase was used or in how
strong a terms cannot be remembered but everyone knew what was meant!. In
September an EGM of the club was held and thankfully the required majority
voted in favour of the scheme. After three and a half years it was now all
systems go and go quickly. Roger Jones began producing the detailed drawings
and contract documentation to be able to go to tender, appoint a contractor and
allow construction to start in March 2003. It had previously been decided that
the earlier in the year the work could start the better for the club. Tenders
were out early December 2002 and in just before Christmas. The club and Roger
Jones met early in January 2003 and after careful consideration the contract
was awarded to Contour Golf Ltd.
Disruption and Damage
At every stage of the process, in every discussion, the Club were very adamant
about their need to be able to continue playing the golf course and expressed
their apprehensions about disruption and damage. Craddockstown Golf Club has a
large active playing membership, a full competition diary and a full diary of
golf societies and corporate visitors. Understandably the revenue and
reputation gained from these was too important to lose. In spite of the
meticulous planning that was going into the construction programme,
reassurances by Roger Jones that disruption would be minimal were rarely
sufficient to appease. Only time and the actualities of the construction
programme were going to prove it, or not, as the case may be.
Construction
As soon as topsoil stripping began in the areas to be worked the real extent
of what was about to happen in the coming weeks could be seen by officials and
members alike. To some it was very exciting, to others it no doubt brought
alarm and disbelief. A six week period of dry weather in March and April
enabled earthworks to progress quicker than expected and put the contractors
ahead of schedule. With over 30,000m3 of material being excavated, carted and
shaped elsewhere around the course the potential for disruption and damage to
the golf course was always there. However, the detailed planning and regular
supervision by Roger Jones and the careful but highly productive approach taken
by Contour Golf has ensured that this has not happened. The members of
Craddockstown Golf Club and the fee paying visitors and golf societies have
continued to play the golf course on a daily basis. At no time has the club had
to endure more than 2 temporary greens in the entire 18 holes and when work in
any area has been completed, play to the permanent green has been resumed. 
A good example of this has been on the 10th hole where a new lake has been
excavated on the approach to and around the green. No sooner was the main
excavation completed, the flag was replaced in the green and golfers played
over the then empty lake. The greenkeeping staff even placed the required red
hazard markers around the perimeter and the new hazard was immediately in play.
The next day the course was host to a golfing society with more than 150
players and there were no complaints to be heard. The overall effect of this
approach has been to generate very positive feedback from members and visitors,
all of whom have been able to experience the features of the new-look golf
course even though they are not yet completed. Similarly, new fairway bunkers
have been shaped and although still to be finally finished, drained and sanded
are giving golfers more to think about as they plot their way around the Co.
Kildare course. The majority opinion has been that they eagerly look forward to
seeing everything grassed and grown and in its new-found splendour.
Bringing each feature of the course back into play in the earliest possible
time frame was always a consideration. In this regard, the reshaping and
reconstruction of existing greenside bunkers and the addition of some new ones
has been carried out very efficiently. The excavation and shaping has been
immediately followed by the turfing of the bunker surrounds. During the work
the temporary green created by the Club is in put into use. Immediately upon
completion (within the same day) the flag is replaced in the permanent green,
the bunkers roped off and treated as ground under repair for play purposes. The
next golfers to that green are confronted by a different aspect to the hole
than they had previously been used to. At this stage it is fair to say that
golfers are now noticing bunkers that they probably didn't realise every
existed before.
All mention of disruption and damage to the course has now disappeared. The
reassurances that Roger Jones gave about minimal disruption are now being
believed.
Communication
Communication has played a vital role in ensuring that the needs of all
parties are met and that progress is smooth and without duress. Lines of
communication were quickly established between Roger Jones, the contractors
site representative Liam Cotter, the golf course superintendent Kevin Byrne and
the club's General Manager Gay Nolan. The current club captain, Pat
Corrigan, has also played a pivotal role in this. Pat has been at the club most
days and as well as being a keen golfer found on the course at every
opportunity, has ensured that the contractors are aware of events happening on
the course and conversely finds out where work is to carried out in the
forthcoming days and what temporary variations to the course are needed, if
any, for the clubs next competition or visiting group. This approach, a very
good lesson in relationship management, is paying dividends for all
concerned.
Progress
Although the Irish climate has taken back some some of the time gains given to
the contractor in the early weeks of the construction, the project is on course
for completion at the end of June. At the time of writing all major earthworks
and shaping have been completed, reshaping of the greenside bunkers on 13 holes
has been completed and topsoiling and drainage is underway.
Specification
Having experienced the problems arising from some of the 'less than well
constructed' elements of the original golf course, in spite of budgetary
constraints, the club have been keen to ensure that the specification of the
upgrade works is not compromised. Industry standards recommended by Roger Jones
have been taken on board by the club and these are the standards being worked
to by the team from Contour Golf.
The Benefits
At the early stages of any project the golf course architect can visualise the
finished product and the composite elements of it. For a client this is much
more difficult and in some cases impossible to appreciate until after
completion. The club knew that they didn't want elements of what they had,
but they weren't necessarily able to visualise what they would have. The
benefits are now becoming fully apparent to them - namely some new greens that
offer different challenges to what they are used to, new tees that lengthen
some holes and offer a different aspect to others, fairway bunkers that add new
character and strategy to holes, reshaped and reconstructed greenside bunkers
that are completely different than the existing and in most cases give a very
different look and feel to each green complex. Probably the greatest impact
will come from the way in which the new lakes are brought into play. Not only
do these look good and change the character of the respective holes
immeasurably but in some areas they are a major factor in the improved drainage
in that area. New pathways and bridges tie in a lot of these new elements. When
all of the new golf course features have grown-in and are open for play the
result will be a golf course that is vastly differently. A golf course that is
more challenging and more rewarding. A golf course that can compete with the
best of its neighbours in the region. A golf course that will be more sought
after and desirable than previously. In years gone by Craddockstown Golf Club
was a well maintained parkland golf course but was always regarded as being
easy and a bit featureless. The same will not be said in the future.
Return on Investment
By the end of the project the club will have invested in excess of half a
million euro, not a huge amount but also not small for a members club that is
not totally 'commercial'. Potential return on investment can be
significant and the investment will undoubtedly be repaid in a very short space
of time. The club already has a long waiting list for membership and entrance
fees have increased. Green fee rates can be increased more than would otherwise
have been the case because the 'product' offered by the club will now
be of a much higher standard. The reputation of the club will be further
enhanced which in turn can generate higher levels of business.
The club is already aware of a number of new opportunities which will be
presented to it with an upgraded course, one of which is the potential spin-off
from the Ryder Cup Matches 2006 being hosted at the nearby K Club.
Lessons to be learnt
Other clubs around the golfing world considering similar upgrade projects can
learn a lot from the Craddockstown example. First and foremost the importance
of hiring a professional golf course architect who will prepare proper drawings
and accurate cost estimates, secondly contracting the works to a specialist
golf course contractor, especially one that has a good reputation for the
standard of their finishing work and one that has proven they can carry out
such works without damaging an existing course. Next is planning, planning
every element in fine detail to avoid disruption and last but certainly not
least communication, making sure the lines of communication are transparent and
get used properly. Day to day communication between the parties directly
involved is much more important than a whole series of after dark meetings and
written reports.
Other clubs either thinking about, or about to embark on similar project
should take note, and take reassurance from the fact that it is perfectly
possible to undertake such a project without disruption to the daily run of
play on the course and without damage to other areas of it. |
|